Scheduling of a School Project Considering Risk Analysis Utilizing Project Management Tool Primavera P6

Open Access Peer Reviewed Crossref DOI

Authors

  • Dinesh Goyal1
  • Hitesh Kodwani2

12Department of Civil Engineering, Sam Global University, Bhopal, India.

Article Information

Published Online
March-April 2023
Pages
522-526
Article Type
Research Article
Check for updates
check update

References

[1] Piyush Pramod Bagade and Prof. Abhijit Bhirud, “Review on construction project management software primavera p6” international
journal of engineering sciences & research technology, ISSN: 2277-9655, January, 2018, PN (110-117).
[2] Poonam Raykar and Ghadge A.N., “Analyzing the Critical Factors Influencing the Time Overrun and Cost Overrun in Construction
Project” International Journal of Engineering Research, Volume No.5, ISSN:2319-6890, 9 Jan 2016, PN (21-25).
[3] A. Ray Chaudhuri, B. Sivakonda Reddy and S.K. nimbal, “Resource Management in Construction Projects – a case study” Engineering Science and Technology: An International Journal (ESTIJ), ISSN: 2250-3498, Vol.2, No. 4, August 2017 PN (660 – 665)
[4] A.R. Nikumbh and S.S. Pimpliker, “Planning and controlling of a National Highway Project- A case study”, Journal of the Indian Road
Congress Paper No.613, April – June 2014 PN (91 – 102).
[5] P M Wale1 , N D. Jain , N R Godhani , S R Beniwal and A A Mir, «Planning and Scheduling of Project using Microsoft Project (Case
Study of a building in India», IOSR Journal of Mechanical and Civil Engineering, ISSN: 2320-334X, Volume 12, Issue 3 Ver. III (May. - Jun.2015), PN 57-63.
[6] Shaik Mohammad, Kunal B. Badgujar, B.A.Konnur and Amarsinh B. Landage “A Review of EVM Analysis with Primavera”;
International Journal of Engineering Research ISSN:23196890(online),2347-5013 Volume No.5, Issue Special 1 9 Jan 2014 PN: 164-167
[7]. Hamid, R. Gupta, Parag S. Mahatme and Taran C. Bhagat “The cost controlling and monitoring of Construction project through earned Value management system” International Journal of Advanced Technology in Engineering and Science www.ijates.com Volume No 03,Special Issue No. 01, March 2013 ISSN (online): 2348 – 7550
[8] P.Dayakar and M.Udhayakumar, «Study on Project Management of an Ongoing Construction project Using MSP Sub Structure”
Volume2 Issue 5 Number2–Oct 2012, PN 202-212.
[9] Stephenson, P. and Fapohunda, J.A. “Optimal Construction Resources Utilization: Reflections of Site Managers’ Attributes. The Pacific Journal of Science and Technology, Vol. 11. No. 2. November 2010 (Fall) PN 105-109.
[10] Tranner, D. S. Stephan Jabasingh and J. Jayalakshmi “Analysis of Cost Controlling In Construction Industries by Earned Value
Method Using Primavera”; Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 4, Issue 6(
Version 1), June 2009, PN.145-153.
[11] Prabhakar, G. P. What is Project Success: A Literature Review. International Journal of Business and Management. September, 2008.
APC from ₹1200 + 18% GST

Peer-reviewed open access₹1200 Indian (₹1400 with DOI)$80 USD internationalpaid after acceptance Peer-reviewed open access₹1200 Indian$80 USD international ₹1200 Indian · $80 intl

  • CrossRef DOI
  • ISSN 2582-8746
  • Open Access
  • Peer Reviewed
  • Plagiarism Checked
  • Google Scholar
Submit Paper